4 in 5 decision-makers agree prioritising upfront costs drives clean energy blowouts

New research reveals two-thirds of major projects commonly face downstream cost overruns as the industry prioritises upfront budgets over lifecycle value

New industry research reveals that the prioritisation of keeping costs low in the short term is unintentionally contributing to higher long-term operational costs, with 81% of project decision-makers admitting that upfront cost is often prioritised over lifecycle cost and long-term value.

Commissioned by energy infrastructure specialist Intium and conducted by Lonergan Research, the study highlights the pressures developers face to keep upfront costs low when getting complex projects off the ground.

More than half (55%) of project decision-makers say early planning decisions often require material changes to scope and budget later on, a risk frequently driven by tight delivery timeframe pressures (38%) and upfront budget constraints (26%).

The pressure to keep up-front costs low is creating a lifecycle value gap. Two-thirds (66%) of decision-makers assert that early planning decisions commonly contribute to downstream project cost overruns, while 60% say they commonly cause project delays.

In fact, 96% of decision-makers report experiencing material negative consequences when early decisions are changed, most commonly cost overruns (36%) and procurement delays (34%). The operational impact is even sharper on utility-scale renewable and power infrastructure projects, where over half (52%) are forced into equipment or technology replacements. Beyond these immediate setbacks, nearly a quarter (26%) warn that such changes ultimately defer the project or reduce its overall commercial viability.

Nathan Rhodes, Executive General Manager at Intium, said the findings reflect an industry working hard under pressure to meet transition targets and financial constraints.

“With the clean energy market moving so rapidly and constrained funding for projects prior to financial close, the pressure to meet tight delivery timeframes often forces a focus on short-term upfront savings and unveils a lifecycle value gap. But this approach opens developers up to longer-term risks. The research shows that key risks to a project’s long-term value, including how it will be built, need to be addressed before commercial assumptions are locked in. Bringing technical, delivery and regulatory expertise in early helps prevent those risks from becoming costly problems later,” said Rhodes.

There is near-unanimous agreement on how to solve this challenge. An overwhelming 94% of decision-makers agree that involving grid connection or power infrastructure expertise earlier in the project lifecycle would help avoid delays and long-term cost blow-outs.

The data makes a clear case that engagement with SMEs like grid specialists, construction contractors and governments at the early concept design stage is critical, with 58% of decision-makers agreeing with this approach. They also confirmed a lack of early commercial (77%), regulatory (70%) and technical (64%) expertise significantly increases the risk of downstream delivery delays and material changes which impact project costs.

Babu Kumar, General Manager of Engineering and Delivery at Intium, noted that bringing engineering and constructability expertise to the table earlier is the most effective way to ensure decisions that are made in the short term are optimised to ensure long-term value.

“Grid connection and power infrastructure remain among the greatest execution challenges in developing renewable energy projects. When we integrate technical grid expertise, government support and early construction advice right at the initial concept design stage, we can engineer solutions for physical infrastructure and regulatory hurdles before capital is locked in, whilst optimising procurement challenges. This approach shifts the focus from simply chasing short term wins to keep project costs down upfront, to ensuring decisions are made at every stage of the project that will drive the optimal long-term lifecycle value of the project.”

Methodology

The research was commissioned by Intium and conducted by Lonergan Research in accordance with the ISO 20252 standard.

The study captured insights from a sample of 53 Australian renewable energy decision-makers actively involved in major clean-energy and power infrastructure projects. While surveys were distributed nationally across both capital city and regional areas, the parameters of the research were heavily focused on respondents operating within the National Electricity Market. The survey was conducted online amongst members of a permission-based panel between 13 October 2026 and 6 November 2026. After interviewing, data was weighted to the latest population estimates sourced from the Australian Bureau of Statistics.

About Intium 

Intium is a specialist provider of high-voltage infrastructure solutions that enable the seamless integration and long-term operation of large-scale renewable energy and storage assets. From complex grid connections, including the design and delivery of substations, switching stations and transmission lines, to Battery Energy Storage Systems, Balance of Plant and electric vehicle charging solutions. With a strong commitment to regional Australia, Intium prioritises the use of local skills, suppliers and contactors, creating long-term economic benefits for the communities in which it operates.

INDEPENDENT NEWS IS IMPORTANT.

Enjoy reading Eco Voice? Please help us by purchasing a GIFT Voucher or send one to a friend and encourage people to purchase trees or seeds via The Native Shop – www.nativeshop.com.au

Plants, seeds & more delivered to your door!

Share it :

Leave a Reply

Your email address will not be published. Required fields are marked *